Led $5M Global SAP Implementation
When Technicolor’s parent company selected SAP as its’ global ERP platform and Guadalajara as the initial implementation site, Kevin was recruited as the global program lead.
Action
- Assessed global requirements, drafted RFP and developed $5M budget
- Selected IBM as global implementation partner, secured budget & 9-month timeline for project and built team of 30 from IBM, Technicolor and 3rd party specialists
Results
- Completed project on-time and under $5M budget
- Redesigned supply chain processes and trained over 1,000 employees enabling facility to grow from 4 manufacturing lines to 100 while reducing unit costs by 20%
“I hired Kevin to lead Technicolor’s worldwide SAP initiative. From drafting the RFP, to staffing and relocating the 25+ person team to Guadalajara, Mexico, to successfully delivering the implementation and expected business benefits – on-time and under budget, Kevin did an exceptional job of managing every aspect of our implementation at the world’s largest DVD plant.”
Chuck Parker, President, Technicolor Home Entertainment